CPMS # (s)
TIP MPMS #
77183
Location
Philadelphia
Service Area
Philadelphia
Line/Corridor:
[L]
Schedule/Status
Design is complete (2023 – 2024).
Construction: 2025 – 2029
Project Description: Improvements to the 34th Street Station on the Market-Frankford Line will make the station fully ADA accessible. The project provides for the installation of elevators and accessibility improvements; renovation of existing platforms and station interior; new signage, lighting and security cameras; and waterproofing improvements.
Budget | Prior Funding | FY 2026 | FY 2027 | FY 2028 | FY 2029 | FY 2030 | FY 2031 | FY 2032 | FY 2033 | FY 2034 | FY 2035 | FY 2036 | FY 2037 | 12-Year Total | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
40.77 | 10.46 | 0.00 | 3.18 | 13.42 | 13.71 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30.31 |