34th Street Station

 2025CB_140_P

CPMS # (s)

CCS34

TIP MPMS #

77183

Location

Philadelphia

Service Area

Philadelphia

Line/Corridor:

[L]

Schedule/Status

Design is complete (2023 – 2024).
Construction: 2025 – 2029

Project Description: Improvements to the 34th Street Station on the Market-Frankford Line will make the station fully ADA accessible. The project provides for the installation of elevators and accessibility improvements; renovation of existing platforms and station interior; new signage, lighting and security cameras; and waterproofing improvements.

Capital Costs by Funding Year ($ in Millions)

Budget

Prior Funding

FY 2026

FY 2027

FY 2028

FY 2029

FY 2030

FY 2031

FY 2032

FY 2033

FY 2034

FY 2035

FY 2036

FY 2037

12-Year Total

40.77

10.46

0.00

3.18

13.42

13.71

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

30.31

 2025CB_140_A