NHSL Viaduct over Schuylkill River

 2025CB_33_P

CPMS # (s)

CABBV

TIP MPMS #

95402

Location

Montgomery

Service Area

Delaware, Montgomery

Line/Corridor:

[M]

Schedule/Status

Design: 2022 – 2024.
Construction: 2024 – 2029

Project Description: The Bridgeport Viaduct at Mile Post 12.81 (Schuylkill River) on the Norristown High Speed Line [M] will be rehabilitated. The project includes steel, concrete, bearing repairs, and painting. The viaduct was constructed in 1911 and is 3,165 feet long.

Capital Costs by Funding Year ($ in Millions)

Budget

Prior Funding

FY 2026

FY 2027

FY 2028

FY 2029

FY 2030

FY 2031

FY 2032

FY 2033

FY 2034

FY 2035

FY 2036

FY 2037

12-Year Total

54.99

2.70

8.94

19.63

12.09

11.64

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

52.30