Willow Grove Station on the Warminster Regional Rail Line
CPMS # (s)
TIP MPMS #
77183
Location
Montgomery
Service Area
Montgomery, Bucks, Philadelphia
Line/Corridor:
Warminster
Schedule/Status
Phase 1: Design (2018 – 2026) is paused. However, $1.2 million is provided for this station to support an existing agreement between SEPTA and Upper Moreland Township. Construction is to-be-determined based on funding availability
Phase 2 will be developed at a later time as funding resources become available.
Project Description: Relocation of Willow Grove Station on the Warminster Regional Rail Line will make the station fully ADA-accessible and address traffic congestion issues on Rt. 611 near the existing station.
Phase 1 includes track realignment and related right-of-way improvements to support
Phase 2 improvements will include new full length high-level center platform passenger shelters; accessible pathways and handrails/ guardrails; improved station access; parking expansion; new signage and lighting; stormwater management systems; and landscaping. Phase 2 total cost is $52.47 M. Of this amount, $1.2 M is funded in the FY 2026 Budget Proposal.
Budget | Prior Funding | FY 2026 | FY 2027 | FY 2028 | FY 2029 | FY 2030 | FY 2031 | FY 2032 | FY 2033 | FY 2034 | FY 2035 | FY 2036 | FY 2037 | 12-Year Total | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1.20 | 0.00 | 1.20 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1.20 |