Willow Grove Station on the Warminster Regional Rail Line

 

CPMS # (s)

CRSWG

TIP MPMS #

77183

Location

Montgomery

Service Area

Montgomery, Bucks, Philadelphia

Line/Corridor:

Warminster

Schedule/Status

Phase 1: Design (2018 – 2026) is paused. However, $1.2 million is provided for this station to support an existing agreement between SEPTA and Upper Moreland Township. Construction is to-be-determined based on funding availability
 
Phase 2 will be developed at a later time as funding resources become available.   

Project Description: Relocation of Willow Grove Station on the Warminster Regional Rail Line will make the station fully ADA-accessible and address traffic congestion issues on Rt. 611 near the existing station.

Phase 1 includes track realignment and related right-of-way improvements to support

Phase 2 improvements will include new full length high-level center platform passenger shelters; accessible pathways and handrails/ guardrails; improved station access; parking expansion; new signage and lighting; stormwater management systems; and landscaping. Phase 2 total cost is $52.47 M. Of this amount, $1.2 M is funded in the FY 2026 Budget Proposal.

Capital Costs by Funding Year ($ in Millions)

Budget

Prior Funding

FY 2026

FY 2027

FY 2028

FY 2029

FY 2030

FY 2031

FY 2032

FY 2033

FY 2034

FY 2035

FY 2036

FY 2037

12-Year Total

1.20

0.00

1.20

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.20

 2025CB_131_A

Willow Grove Station Concept – Subject to Change